I Brought Receipts · Part 5 of 6
Who Got the Money?
September 3, 2026 · By Ajai Dittmar
Part Four: Follow the Contracts
A fool and his money are soon parted.
But it wasn’t their money. It was ours.
In Part Three, I followed the public money coming into Cedar Rapids after the 2008 flood.
Federal disaster money. State flood mitigation money. Local Option Sales Tax revenue. Bonds. Grants.
Different pockets. Same enormous public undertaking.
But knowing where the money came from only answers half the question.
Now we follow where it went.
And this is where the names from the earlier parts of this series begin showing up again.
Engineers. Planners. Consultants. Program managers.
Some helped develop the plans.
Some helped design the flood control system.
Some managed its implementation.
Some are still working on it today.
This part is not about guessing whether anyone was paid too much. It is not an accusation that receiving a government contract is improper.
It is something much simpler.
Who did Cedar Rapids hire, what were they hired to do, and how much public money did the City authorize for those contracts?
There is one important distinction.
The figures below are authorized contract amounts unless specifically identified as actual expenditures.
A $10 million contract does not prove that $10 million was ultimately paid.
I am not going to turn contract ceilings into checks that I cannot prove were written.
With that understood, let’s follow the contracts.
RECEIPT ONE
HR Green: The West Side
For the west side of the Cedar River, one company immediately stands out.
HR Green.
City records identify HR Green as the designer of the West Side Flood Control System.
Contract No. 331001-01 became a long-running professional services agreement that was repeatedly amended as the flood control system developed.
By March 11, 2025, the contract had reached:
$30,937,310


That was after 23 amendments.

The City’s amendment history identifies an original contract amount of $3,409,543 and documents the amendments that increased the authorized contract amount to $30,937,310.
The scope was not simply described as generic engineering work.
City documents describe HR Green’s work as including:
- west-side levees and floodwalls
- pump stations
- hydraulic modeling
- construction management
- preliminary flood-control design
- survey work
- certification packages for future accreditation
- grant-funding assistance
- real-estate coordination
That matters.
This is not money attached vaguely to “flood protection somewhere in Cedar Rapids.”
This contract includes documented work on the west side and in Time Check itself.
Then another contract appeared.
On July 8, 2025, the City approved a separate Professional Services Agreement with HR Green for:
$535,270

Contract No. 331001-04 covered West Side Flood Mitigation System planning and coordination services for FY2026.
Using only these two documented agreements, Cedar Rapids had therefore authorized at least:
$31,472,580
in HR Green professional-services contract value connected to the West Side Flood Control System.
That number requires an important distinction.
$31,472,580 is authorized contract value. It is not a claim that HR Green had already been paid every dollar of that amount.
Those are two different things.
But the contracts are documented.
The authorized amounts are documented.
And the scope of work is documented.
RECEIPT TWO
The City Was Tracking Flood-Control Expenses Specifically to Time Check
Before getting to Anderson-Bogert, there is another important receipt in the City’s own Flood Control System financial records.
By June 2016, Cedar Rapids was separately reporting Flood Control System expenses identified specifically with Time Check.
The City’s preliminary report lists:
Time Check Area Prop Acq — $5,232
GRI-TC-EHP-Time Check — $149,789
GRI-TC-ACQ-Time Check — $309,002
GRI-TC-DEMO-Time Check — $34,930
GRI-TC-MGMT-Time Check — $68,832
GRI-TC-ENGR-Time Check — $1,266,483
Together, those six Time Check entries total:
$1,834,268
And one category accounts for most of that amount.
Engineering: $1,266,483
The same City report states that preliminary Flood Control System expenses through June 2016 totaled approximately $16 million.
It also states that the majority of the expenses reported for June related to design and engineering.
That matters.
By this point, Time Check was not simply appearing in planning documents.
The City’s own financial records contained separate expense entries specifically identified with Time Check, including acquisition, demolition, management and engineering work.
And the largest of those documented Time Check expenses was engineering.

RECEIPT THREE
Anderson-Bogert: At the Table, Then Managing the Program
Another recurring name appears in Cedar Rapids Flood Control System records.
Anderson-Bogert Engineers & Surveyors, Inc.
The firm’s documented involvement with the Flood Control System appears in City records years before the later multimillion-dollar program-management agreement.
On May 2, 2016, Cedar Rapids held a joint meeting of the Flood Control System Committee and the Finance & Administrative Services Committee.
The City agenda included:
2016 Design/Bid Activities — Bill Bogert — Anderson Bogert


Anderson-Bogert appears in Cedar Rapids Flood Control System committee records by May 2016.
The May 2016 agenda does not establish that the work discussed at that meeting was specific to Time Check.
It does establish that Anderson-Bogert was already participating in the broader Flood Control System process by May 2016.
That involvement continued.
On December 20, 2022, the Cedar Rapids City Council approved a Professional Services Agreement with Anderson-Bogert Engineers & Surveyors, Inc. for an amount not to exceed:
$395,288
for program management services for the Cedar Rapids Flood Control System project.

Then came the amendments.
On June 27, 2023, the Cedar Rapids City Council approved Amendment No. 1 for an amount not to exceed:
$1,472,703
for the FY2024 work plan associated with overall program management services in connection with the Cedar Rapids Flood Control System project.
The same record identifies the original contract amount as $395,288 and the resulting contract amount as:
$1,867,991

One year later, the contract amount increased again.
On June 11, 2024, the Cedar Rapids City Council approved Amendment No. 2 for an amount not to exceed:
$1,151,762
for Flood Control System program management services.
The City identified the original contract amount as $395,288 and listed the resulting contract amount as:
$3,019,753

The supporting City paperwork for Amendment No. 2 provides another important piece of the timeline.
The City stated that Anderson-Bogert had been engaged in Cedar Rapids Flood Control System management for:
more than eight years
The same City record describes Anderson-Bogert as providing program-management assistance for both west- and east-side design consultants, including assistance with planning, implementation, scheduling, cost control, and design progress for the overall Flood Control System.



The agreement continued.
The amendment sequence also includes Amendment Nos. 3 and 5. I have not located the underlying documents for those amendments, so I have not assigned either one a scope or dollar amount in this article.
2025: Amendment No. 4
On May 27, 2025, the Cedar Rapids City Council approved Amendment No. 4 for an amount not to exceed:
$893,655
for engineering and program management services in connection with the Flood Control System Program Management project.
The City listed the resulting contract amount as:
$3,913,408

The agreement appears again in City records the following year.
Amendment No. 5 also falls between the documented 2025 and 2026 actions. The records reviewed here do not establish what that amendment changed, so I am not assigning it a scope or dollar amount without the underlying document.
The March 10, 2026 Cedar Rapids City Council agenda listed Amendment No. 6 for an amount not to exceed:
$1,213,614
for the Flood Control System Program Management project.
The agenda identified the original contract amount as $395,288 and listed the total contract amount with Amendment No. 6 as:
$5,127,022
Contract No. 331001-03.

There is an important distinction here.
$5,127,022 is the total contract amount listed by the City with Amendment No. 6.
It is not a claim that Anderson-Bogert had already been paid every dollar of that amount.
It is not a claim that Bill Bogert personally received that money.
And the 2016 committee record is not being presented as proof of Time Check-specific work.
What the records establish is narrower and clearer.
May 2016: Anderson-Bogert appears in City Flood Control System committee records.
December 2022: the City approved a $395,288 Flood Control System program-management agreement with the firm.
June 2023: the City approved an amendment bringing the contract amount to $1,867,991.
June 2024: the City approved another amendment bringing the contract amount to $3,019,753. Supporting City paperwork stated that Anderson-Bogert had already been engaged in Flood Control System management for more than eight years.
May 2025: the City approved an amendment bringing the contract amount to $3,913,408.
March 2026: a City Council agenda listed the contract amount with Amendment No. 6 at $5,127,022.
The records reviewed here also show gaps at Amendment Nos. 3 and 5. Those underlying amendments have not been used to make claims about scope or cost in this article.
Anderson-Bogert’s documented involvement with the Cedar Rapids Flood Control System predates the 2022 program-management agreement by more than six years.
RECEIPT FOUR
Michael Van Valkenburgh Associates: Updating the Greenway Parks Plan
Flood control is not the only plan shaping the west-side river corridor.
There is also the greenway.
On July 11, 2023, the Cedar Rapids City Council approved a contract with Michael Van Valkenburgh Associates, Inc., or MVVA, to update the City’s Greenway Parks Plan for the Parks and Recreation Department.
The contract amount was:
$262,800

The Greenway Parks Plan update also included work beyond landscape design.
Landwise Advisors identifies itself as part of the Cedar Rapids project team and states that its work included economic impact analysis and funding analysis for the updated Greenway Parks Plan.

And the finished plan brings the story directly back to Time Check.

Among the features shown or identified in the plan are promenades, play areas, sports areas, river overlooks, paddle access and other recreational amenities.
And, yes:
the canoe safari.
RECEIPT FIVE
Stanley Consultants: The East Side Comparison
Stanley Consultants belongs in this story, but with an important distinction.
This is east-side Flood Control System work.
City records identify Stanley Consultants with the East Side Flood Control System under Contract No. 331001-02. This contract is not being presented as a Time Check or west-side expenditure.
The east side is also different because the U.S. Army Corps of Engineers is directly involved in constructing the east-side portion of the Cedar Rapids flood-risk-management project in partnership with the City.

On April 14, 2026, the Cedar Rapids City Council agenda listed Amendment No. 28 to Stanley Consultants’ Professional Services Agreement for the Cedar Rapids Flood Mitigation Services, East Side Phase 1 Consulting Services project.
The agenda identified the original contract amount as $3,959,599 and listed the total contract amount with Amendment No. 28 as:
$52,412,348

$52,412,348 is the total contract amount listed by the City. It is not a claim that Stanley Consultants had already been paid every dollar of that amount, and it is not being added to any Time Check or west-side total.
October 2026: The Contract Trail Continues
The October 6, 2026 agenda, item 21(l), lists Stanley Amendment No. 30: up to $309,100, with a resulting East Side Phase 1 contract total of $52,890,448. The original remains $3,959,599. This extends the April record above; it is not a separate contract to add to that earlier total.
T.Y. Lin International: Bridge and Riverfront Consulting
Item 21(n) lists T.Y. Lin International Amendment No. 15 for FCS Bridge and Riverfront Improvements: up to $633,419.88, bringing Contract No. 3316410-01 to $16,151,996.85, from an original $3,287,086.
These are proposed contract amounts, not verified payments. Approval remains unconfirmed. The agenda text is available in a readable archive.
RECEIPT SIX
Sasaki Associates: Planning the Post-Flood Future
City records identify Sasaki Associates as the overall prime consultant for the Cedar Rapids River Corridor Redevelopment, with Stanley Consultants working under Sasaki on the evaluation of flood-mitigation proposals.
The City’s River Corridor Redevelopment Plan chronology shows that on June 17, 2008, just days after the flood, the Cedar Rapids City Council expanded the Sasaki/JLG scope of work to include the larger flood-impacted area.
The expanded scope included planning for reinvestment in river-corridor neighborhoods, workforce housing, measures to enhance flood protection, and neighborhood and development options.

The same chronology shows how quickly the flood-control planning process was taking shape.
In July 2008, the City hired Stanley Consultants to coordinate with the U.S. Army Corps of Engineers and develop flood-management options for Cedar Rapids.
By July 29, 2008, the City was holding the first of three River Corridor Redevelopment Plan open houses.
On September 24, 2008, the City Council held a four-hour work session on flood-management strategy and the River Corridor Plan.
And on October 1, 2008, the Council selected a preferred flood-management strategy for public comment and review.
Sasaki’s significance in this contract trail is therefore not simply that the firm later appears in a planning document.
The City’s own chronology places Sasaki in the post-flood planning process within days of the flood, while decisions about reinvestment, neighborhoods, development and flood protection were still being formed.
That matters because the contracts documented later in this article did not begin with construction.
They followed a planning process that was already addressing flood protection, housing, neighborhood reinvestment and development.
RECEIPT SEVEN
ProSource Technologies: The Acquisition Side
Planning and engineering were only part of the Flood Control System.
The City also hired outside professionals to provide acquisition-related services.
ProSource Technologies, LLC appears in Cedar Rapids records providing right-of-way and acquisition services connected directly to the Flood Control System.
But ProSource’s acquisition work in Cedar Rapids goes back much further.
The City’s December 3, 2013 agenda lists Amendment No. 10 to ProSource Technologies’ Flood Related Property Acquisition Services for CDBG Greenway Area, Construction Study Area and Neighborhood Revitalization Area contract. The original contract was $4,859,200, and Amendment No. 10 brought the total authorized contract amount to:
$15,454,579
Contract/CIP #0809-040.

On June 25, 2019, a City Council agenda listed Amendment No. 7 to an existing ProSource contract for right-of-way acquisition support services. The amendment added up to $100,000 for additional services for the City’s Flood Control System project and listed the total contract amount as
$700,000
Contract No. PUR0515-222.

Later that same year, the City established a separate ProSource contract focused specifically on Cedar River flood-risk-management acquisitions.
On December 17, 2019, the City Council agenda listed a contract with ProSource Technologies for acquisition services for Cedar River flood risk management for an amount not to exceed:
$898,083
Contract No. PUR1019-067.

That second contract continued.
The City’s June 27, 2023 supporting paperwork states that the $898,083 contract began January 1, 2020 and documents a series of amendments and renewals. The same paperwork identifies ProSource personnel classifications that included acquisition/title project management, acquisition and relocation specialists, and acquisition specialists.
On June 27, 2023, the City Council approved Amendment No. 6, renewing that acquisition-services contract for another year for an amount not to exceed:
$875,000
The City minutes identify the original contract amount as $898,083 and the renewal contract amount as $875,000.

A HUD Office of Inspector General audit provides additional context for the earlier acquisition work. The audit examined a master professional services contract whose original proposal was submitted jointly by three companies, including ProSource Technologies.
HUD OIG reported that Cedar Rapids executed six contract modifications that increased that master contract to more than:
$12 million
As of June 12, 2012, Cedar Rapids had spent:
more than $9.3 million
under that master professional services contract. Those figures should not be read as $9.3 million paid solely to ProSource.

ProSource is included here for a simple reason.
The earlier receipts document firms involved in planning, engineering, program management and greenway design.
ProSource documents the acquisition side.
WHAT THE RECEIPTS SHOW
This started with a simple question.
Who did Cedar Rapids hire, what were they hired to do, and how much public money did the City authorize for those contracts?
The answer took me through years of planning, engineering, program management, greenway design and property acquisition.
Some of the figures in this article are authorized contract amounts. Others are documented expenditures. I have kept those separate because they are not the same thing.
And none of these contracts, by themselves, prove wrongdoing.
What they do prove is the scale of the undertaking.
Cedar Rapids had planners.
Engineers.
Program managers.
Acquisition specialists.
Consultants working with other consultants.
Federal agencies.
State agencies.
Committees.
Studies.
Contracts.
Amendments.
Plans for flood protection.
Plans for redevelopment.
Plans for what the land would become after the homes were gone.
And throughout all of it, there were people living here.
The City’s post-flood acquisition programs were described as voluntary.
Many of my neighbors did not experience them that way. They felt forced out.
I am not going to soften that.
They watched homes disappear around them. They watched their neighborhoods change. They watched decisions about their future move forward.
Our family stayed.
Eighteen years after the 2008 flood, the City is still pursuing our property.
And that brings me to the final receipts.
THEY TALKED ABOUT US
In August 2026, while our petition was circulating and questions about our property were growing, City staff were communicating internally about our property, the petition and the City’s public response.
They could talk about us to each other.

Then the City took the discussion public.
On August 7, 2026, Cedar Rapids published a public statement addressing our property, the Flood Control System, acquisition history, appraisals, offers and the City’s position on why the property was being pursued.
They could talk about us on social media.


They could talk about us with the media.
They could talk about us during public meetings.
They could discuss what should happen to our home in front of an audience.
What was remarkably difficult to find was evidence that the people responsible for the Flood Control System and property acquisition had actually sat down with us.
Then, on August 24, 2026, an email arrived from Mayor Tiffany O’Donnell.
The subject was:
Connecting
The message asked whether I had time for a call that evening.
It came the night before the City Council was scheduled to act on the total acquisition of our home.
I did not see the unopened email until around midnight.


The following day, the City Council voted to move forward with the total acquisition of our property, referring it to the Linn County Compensation Commission despite more than 2,600 petition signatures asking them not to proceed. Of those, 200 signatures were collected in person from people who did not have access to the online petition.
Then came the receipt that, for me, puts everything else in this article into perspective.
On August 28, 2026, Cedar Rapids Public Works responded to my open records request seeking documentation of meetings concerning our property.
The City’s response stated that Flood Control System staff had not met with the property owner during the requested period.
It also stated that Real Estate staff were not aware of meetings with Gregory Vail, Ajai Dittmar, or anyone acting on their behalf concerning 1426 1st Street NW since the Flood Control System entered its implementation phase in 2015.

That is the contrast I cannot ignore.
The City could discuss our property internally, publicly, with reporters and during City Council meetings.
It could hire people to plan, engineer, manage and acquire.
It could even hire people to plan what would happen to the land afterward.
But the people living in the home were largely left out of the conversation.
I was here.
Greg was here.
Our home was here.
And when I finally asked for the records, the City said Flood Control staff had not met with the property owner and Real Estate staff were not aware of meetings with us or our representatives.
One email asking for a phone call the night before our home was on the chopping block does not erase that history.
After everything documented in this series, I keep coming back to something much simpler than the contracts and much smaller than the dollar amounts.
For eighteen years, decisions affecting this neighborhood and eventually our home moved forward through plans, contracts, committees and public meetings.
We were here the entire time.
The City had plenty to say about our property. What it did not have was a documented history of sitting down with us.
We are still here.
And the conversation still has not happened.